|
1
|
- Anshel J. Schiff
- Precision Measurement Instruments
- 27750 Edgerton Rd.
- Los Altos Hills, CA 94022
|
|
2
|
- Correct IEEE 693 procedures for the qualification of transformer
bushings
- Correct IEEE 693 procedures for the qualification of hollow-core
composite insulators
- Need for a technical review of IEEE 693 testing methods
- Need to test an improved retainer ring for retrofitting transformer
bushings and evaluating it on a 500 kV bushing
- MCEER establishing Electric Utility Consortium
|
|
3
|
- IEEE 693 qualification tests on a 1980 vintage, GE Type U 230 kV
transformer bushing did not cause oil leaks, porcelain slipping, or
porcelain cracks
- Additional tests above IEEE 693 to the full capacity of the PEER
(Richmond Test Facility) shake table could not cause failure
- In the 1994 Northridge earthquake about 25 of these bushings slipped and
developed permanent oil leaks so that they had to be replaced
|
|
4
|
- Bushings are qualified by testing without being mounted on a transformer
- Bushings are attached to a stiff support structure for qualification
- Qualification base motions are doubled to account for the amplification
introduced by the transformer
- Qualification base motions are doubled again to account for
uncertainties in the failure mode (Tested to the Performance Level)
- These tests have not captured the influence of the transformer on
bushing performance
|
|
5
|
- EPRI Consortium of Utilities have done research on composite CVTs
- IEEE 693 requires a pull test to 1/2 the SML load and measures the top
deflection
- The top deflection forms the acceptance criterion for dynamic tests
- Damage to the composite assembly can increase damping and reduce
stiffness of the unit
- The standard assumes that the increased flexibility will cause damaged
units to exceed the acceptance criterion
- Post-vibration pull test show that units that pass IEEE 693 criterion
would be considered to have failed
|
|
6
|
- Based on three qualification test that I have been involved with (the
two above and one for disconnect switches) all have had flawed
qualification methods
- IEEE 693 has been deficient in allowing the use of flawed measuring
methods
- IEEE 693 has acceptance criteria that do not adequately evaluate the
earthquake performance of tested equipment
- Commercial test laboratories uncritically follow the standard
- There is a need for a detailed review of IEEE 693 by individuals who are
familiar with testing to monitor
the qualification of equipment at commercial testing laboratories
|
|
7
|
- Uniform seismic input criteria established - facilitates manufacturers
to incorporate seismic design as part of normal design process of new
equipment
- Test and analysis methods standardized for qualification
- Uniform acceptance criteria are established
- Procedures are tailored to each type of equipment so that past
earthquake performance and unique characteristics of the equipment can
be taken into account
|
|
8
|
- Slipping between the transformer
bushing flange and porcelain can cause permanent oil leak after an
earthquake
- This requires that the bushing be changed and puts the transformer out
of service
- Tests have shown that a retainer ring can prevent this on 230 kV
bushings
- An improved ring needs to be evaluated and tested on a 500 kV bushing
|
|
9
|
- MCEER and its predecessor (NCEER) have had a focus area on lifeline
systems since their inception
- To improve the opportunity for utilities to guide the program for
electrical power systems the Electric Utilities Consortium is being
formed
- Participating utilities will have Flagship Partner membership in the
center
- Participating utilities will have seats on the center's Industry
Advisory Board and the MCEER-EUC Technical Oversight Committee
|