Notes
Slide Show
Outline
1
Improving IEEE 693 Test Procedures,
Retrofitting Transformer Bushing to Improve Seismic Performance, and MCEER-EUC
  • Anshel J. Schiff
  • Precision Measurement Instruments
  • 27750 Edgerton Rd.
  • Los Altos Hills, CA 94022


2
Key Power Systems Issues Discussed
  • Correct IEEE 693 procedures for the qualification of transformer bushings
  • Correct IEEE 693 procedures for the qualification of hollow-core composite insulators
  • Need for a technical review of IEEE 693 testing methods
  • Need to test an improved retainer ring for retrofitting transformer bushings and evaluating it on a 500 kV bushing
  • MCEER establishing Electric Utility Consortium
3
Correct IEEE 693 Procedures for the Qualification of Transformer Bushings
  • IEEE 693 qualification tests on a 1980 vintage, GE Type U 230 kV transformer bushing did not cause oil leaks, porcelain slipping, or porcelain cracks
  • Additional tests above IEEE 693 to the full capacity of the PEER (Richmond Test Facility) shake table could not cause failure
  • In the 1994 Northridge earthquake about 25 of these bushings slipped and developed permanent oil leaks so that they had to be replaced
4
IEEE 693 Transformer Bushing Qualification
  • Bushings are qualified by testing without being mounted on a transformer
  • Bushings are attached to a stiff support structure for qualification
  • Qualification base motions are doubled to account for the amplification introduced by the transformer
  • Qualification base motions are doubled again to account for uncertainties in the failure mode (Tested to the Performance Level)
  • These tests have not captured the influence of the transformer on bushing performance
5
Correct IEEE 693 Procedures for the Qualification of Hollow-Core Composite Insulators
  • EPRI Consortium of Utilities have done research on composite CVTs
  • IEEE 693 requires a pull test to 1/2 the SML load and measures the top deflection
  • The top deflection forms the acceptance criterion for dynamic tests
  • Damage to the composite assembly can increase damping and reduce stiffness of the unit
  • The standard assumes that the increased flexibility will cause damaged units to exceed the acceptance criterion
  • Post-vibration pull test show that units that pass IEEE 693 criterion would be considered to have failed
6
Need for a Technical Review of IEEE 693 Testing Methods
  • Based on three qualification test that I have been involved with (the two above and one for disconnect switches) all have had flawed qualification methods
  • IEEE 693 has been deficient in allowing the use of flawed measuring methods
  • IEEE 693 has acceptance criteria that do not adequately evaluate the earthquake performance of tested equipment
  • Commercial test laboratories uncritically follow the standard
  • There is a need for a detailed review of IEEE 693 by individuals who are familiar with testing to  monitor the qualification of equipment at commercial testing laboratories
7
Overall Assessment of IEEE 693 Good
  • Uniform seismic input criteria established - facilitates manufacturers to incorporate seismic design as part of normal design process of new equipment
  • Test and analysis methods standardized for qualification
  • Uniform acceptance criteria are established
  • Procedures are tailored to each type of equipment so that past earthquake performance and unique characteristics of the equipment can be taken into account
8
Need to Test an Improved Retainer Ring for Retrofitting Transformer Bushings
  • Slipping  between the transformer bushing flange and porcelain can cause permanent oil leak after an earthquake
  • This requires that the bushing be changed and puts the transformer out of service
  • Tests have shown that a retainer ring can prevent this on 230 kV bushings
  • An improved ring needs to be evaluated and tested on a 500 kV bushing


9
MCEER Establishing Electrical Utilities Consortium
  • MCEER and its predecessor (NCEER) have had a focus area on lifeline systems since their inception
  • To improve the opportunity for utilities to guide the program for electrical power systems the Electric Utilities Consortium is being formed
  • Participating utilities will have Flagship Partner membership in the center
  • Participating utilities will have seats on the center's Industry Advisory Board and the MCEER-EUC Technical Oversight Committee